In concrete construction, 28 days is one of the most familiar milestones.
After 28 days of standard curing, concrete specimens are tested for compressive strength. If the test results meet the specified requirements, the concrete passes the corresponding strength acceptance criteria.
But there is an important point that is often overlooked:
Reaching the 28-day compressive strength does not mean that concrete has completed its shrinkage process.
Concrete begins to shrink from an early stage after casting. Some shrinkage develops relatively quickly, while other forms may continue for months or even years.
Understanding concrete shrinkage is essential for crack control, construction scheduling, plastering and finishing work, and long-term durability.
01. Concrete Shrinkage Involves Multiple Mechanisms
The two major types of concrete shrinkage are autogenous shrinkage and drying shrinkage. Temperature-related volume changes should also be considered separately in engineering assessments.
Autogenous Shrinkage
Autogenous shrinkage is primarily associated with cement hydration.
As hydration progresses, the relative humidity inside the cement paste decreases, creating a self-desiccation effect that leads to volume reduction.
Unlike drying shrinkage, autogenous shrinkage does not depend on moisture escaping into the external environment.
It is particularly important in low water-to-binder ratio and high-strength concrete.
Autogenous shrinkage generally develops more rapidly at early ages, with its rate gradually decreasing as hydration slows down.
Drying Shrinkage
Drying shrinkage occurs when moisture gradually moves from inside the concrete toward its surface and evaporates into the surrounding environment.
As moisture is lost, changes in the cement paste's pore structure generate volume reduction.
Compared with autogenous shrinkage, drying shrinkage generally develops over a much longer period. It may continue for months or even years and is an important contributor to long-term concrete cracking.
Both types of shrinkage can occur simultaneously rather than as two completely separate stages.
02. How Long Does Concrete Drying Shrinkage Last?
Drying shrinkage is not a process that ends after 28 days. It develops gradually over an extended period.
For general engineering understanding, the following milestones help illustrate its development:
Drying shrinkage has already developed significantly, but a considerable portion may still remain.
Shrinkage continues to develop as more early-stage moisture loss takes place.
A substantial portion of drying shrinkage may have occurred, although further changes are still possible.
The shrinkage rate generally decreases, but this does not mean that all concrete has completely stopped shrinking.
These milestones are general references, not fixed percentages or universal acceptance criteria.
The actual shrinkage rate depends on several factors, including ambient relative humidity, temperature, member thickness, water-to-binder ratio, aggregate properties, and curing conditions.
For example, thin concrete members may experience moisture loss more rapidly than thicker sections because moisture has a shorter migration path to the surface.
This helps explain why some concrete structures show no obvious cracks initially, yet new shrinkage cracks may appear months or even years after construction.
03. How Much Does Concrete Shrink, and Why Can Small Changes Cause Cracks?
Concrete shrinkage is commonly expressed as microstrain (με).
Under typical engineering conditions, long-term total shrinkage may reach several hundred microstrains, although the actual value varies depending on material composition, member dimensions, and environmental conditions.
For example, assume a concrete member has a shrinkage strain of 500 με.
For a member that is 1 meter long, the theoretical free shrinkage deformation would be approximately 0.5 mm.
At 1,000 με, the corresponding free shrinkage deformation would be approximately 1 mm.
These dimensional changes may appear insignificant. However, when concrete is restrained by foundations, adjacent structural members, reinforcement, or other elements, shrinkage deformation can generate internal tensile stress.
When this tensile stress exceeds the concrete's tensile capacity at that age, shrinkage cracking may occur.
Concrete cracks are not always caused by insufficient strength. They may also result from restrained shrinkage deformation.
This is why proper curing, temperature and moisture management, and appropriate structural detailing remain important even after concrete has passed its compressive strength tests.
04. 28 Days Is a Strength Milestone, Not the End of Shrinkage
The 28-day compressive strength test is an important quality assessment in concrete construction. However, it should not be interpreted as proof that all concrete properties have fully stabilized.
Effective concrete quality management requires attention to several aspects:
Maintain adequate moisture and prevent excessive early-age water loss.
Reduce the risk of cracking caused by temperature gradients and temperature fluctuations.
Optimize the water-to-binder ratio and the composition of cementitious materials and aggregates.
- Construction and Structural Design:
Provide appropriate construction joints, expansion joints, and necessary crack-control measures.
Schedule plastering, finishing, and other subsequent work according to actual structural conditions and project requirements.
Concrete shrinkage is a long-term process. A 28-day strength report alone cannot determine the risk of future cracking.
28 days is a milestone for evaluating concrete strength. Shrinkage, however, requires a much longer period of observation and management.
Effective concrete quality control should focus not only on early-age strength but also on long-term dimensional stability.